SHELL HAS LOST a licence to operate a gas terminal at Bellanaboy in Co Mayo after a court challenge by a local resident.

The licence had been issued by the Environmental Protection Agency in June of this year but today the Commercial Court conceded the case brought by Martin Harrington and rescinded the licence.

Harrington had argued that the EPA failed to carry out a proper environmental impact assessment before granting the licence for Shell to operate the Mayo gas refinery and the Commercial Court found there were defects in the carrying out of the assessment.

The EPA said it accepted the decision made by the court to quash the licence and it will now consider the verdict. The agency had not opposed Harrington in his action and will pay his legal costs.

In a statement, Shell E&P Ireland Limited said the developments in court today will be examined and following consultation with the relevant bodies, it “fully anticipates that the required licences will be in place” when the pipelines starts production.

SOURCE

RELATED ARTICLE IN THE IRISH TIMES

Screen Shot 2013-05-11 at 14.06.27

Revised licence for Shell gas terminal at Ballinaboy quashed

Shell E&P Ireland was a notice party to the proceedings and, in seeking last August to have them fast-tracked, said the case had “significant potential commercial consequences” for the €2.7 billion Corrib gas project.

By Mary Carolan: Tuesday Oct 15, 2013

The controversial Shell Corrib gas pipeline project in Co Mayo has suffered a major setback after the Commercial Court today granted an order quashing the revised licence issued for the Shell gas terminal at Ballinaboy.

The Environmental Protection Agency, which issued the licence last June, conceded in court today that Martin Harrington was entitled to that order arising from defects in relation to the board’s carrying out of an Environmental Impact Assessment (EIA) concerning the terminal development.

Mr Justice Peter Kelly granted the order to Mr Harrington, Doohoma, Ballina, Co Mayo, after the EPA said it was not opposing his legal challenge to the revised Integrated Pollution Prevention and Control (IPPC) licence issued by the agency to Shell E&P Ireland. The EPA will also pay Mr Harrington’s legal costs.

The licence had permitted the operation of a gas refinery and combustion installations, with a rated thermal output of 50MW or greater, at Ballinaboy Bridge gas terminal, Bellagelly South, Co Mayo.

Shell E&P Ireland was a notice party to the proceedings and, in seeking last August to have them fast-tracked, said the case had “significant potential commercial consequences” for the €2.7 billion Corrib gas project.

The company said construction of the terminal has been largely completed and it was intended to begin commissioning the terminal gas infrastructure, under the revised IPPC licence, on April 1st, 2014. It was intended it would be carried out by importing natural gas through the terminal’s connection with the national grid through which gas from the Corrib field will later be transported to the market, the company said.

The company added it envisaged work to be carried out related to the project to the end of this year would cost some €170 million under existing contracts and ongoing construction and maintenance costs for the terminal, overall project team and offices.

The company had also recruited a significant number of local staff to operate the terminal, it added. In all the circumstances, the company said it was anxious the case be decided as soon as possible.

In his judicial review challenge, Mr Harrington argued that, in issuing the revised licence, the EPA had failed to carry out an EIA in a manner that met the requirements of various EU directives, including the Habitats Directive.

He also argued that an amendment made to an earlier IPPC licence did not conform with provisions of the EPA Act insofar as it sought to carry out an EIA subsequent to the making of the decision.

He claimed the EPA erred in law in seeking to retrospectively carry out an EIA at a meeting of the EPA board held on June 25th, 2013, when the decision in respect of the IPPC licence had already been made. Such an assessment must be carried out before a decision is made on a licence, he argued.

Insofar as the EPA purported to carry out an EIA on June 25th, 2013, the record of that EIA as contained within the minutes of the board meeting did not amount to an assessment that met the requirements of the EU directives, he said.

RELATED: Setback for Corrib pipeline as revised licence is quashed Independent.ie: 16 October 2013

This website and sisters royaldutchshellgroup.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, and shellnews.net, are owned by John Donovan. There is also a Wikipedia segment.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Comment Rules

  • Please show respect to the opinions of others no matter how seemingly far-fetched.
  • Abusive, foul language, and/or divisive comments may be deleted without notice.
  • Each blog member is allowed limited comments, as displayed above the comment box.
  • Comments must be limited to the number of words displayed above the comment box.
  • Please limit one comment after any comment posted per post.