Kazakhstan to delay work on vast oil field by three more years

Kazakhstan is planning a three-year halt to work on the main phase of the super-giant Kashagan oil field development, as international oil companies Royal Dutch Shell and Exxon Mobil fight to convince the country’s oil ministry to back a simplified design, which would slash costs by $18bn (£11bn) to $50bn.

The Kazakhs are considering shelving the new simplified design, and keeping the field producing at its initial rate of 375,000 barrels per day (bpd) for at least three years. Photo: Getty

Richard Orange
By Richard Orange, in Astana 11:30PM BST 04 Apr 2011

The delay, if approved, could push the start of full production from the field well into the next decade, making it all but impossible for Shell and its partners to make an acceptable profit before the contract expires in 2037.

The Kazakhs are considering shelving the new simplified design, and keeping the field producing at its initial rate of 375,000 barrels per day (bpd) for at least three years, after which the NCOC consortium could use a greater understanding of the geology to produce a better design for the second phase, when production is expected to hit 1.5m bpd.

When the oil field was discovered in 2000, it was the biggest find in more than 30 years, with reserves of 9bn-13bn barrels. But under Italy’s ENI, the company chosen to operate the project, costs soared to $136bn.

The start date also slipped from the target of 2005.

NCOC’s new design for the field was informally presented to the Kazakhs at the end of last year. An official said Kazakh oil ministry officials were unhappy with NCOC’s decision to use a new geological model of the field, which was presented last month by Exxon.

“Frankly, we laugh at their model,” the official said. “It’s based on too many assumptions and the data is very doubtful.”

Over the next three months, the consortium will present their model of how oil will flow as it is produced, after which the Kazakhs will make a final decision on the freeze.

Shell, Exxon Mobil, Total and KazMunaiGaz all have a 16.81pc stake in the field. ConocoPhillips has 8.4pc, and Japan’s Inpex 7.56pc.

SOURCE ARTICLE

This website and sisters royaldutchshellgroup.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, and shellnews.net, are owned by John Donovan. There is also a Wikipedia segment.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Comment Rules

  • Please show respect to the opinions of others no matter how seemingly far-fetched.
  • Abusive, foul language, and/or divisive comments may be deleted without notice.
  • Each blog member is allowed limited comments, as displayed above the comment box.
  • Comments must be limited to the number of words displayed above the comment box.
  • Please limit one comment after any comment posted per post.