Royal Dutch Shell Plc  .com Rotating Header Image

Decom Offshore 2016: Shell’s Brent Delta decom unaffected by delay of giant lifting vessel

 

Screen Shot 2016-05-30 at 22.45.42

Written by Phil Allan – 26/05/2016 7:00 am

A senior executive from Shell’s multi billion dollar Brent field decommissioning team said the delay in deploying the enormous would not add to the cost of the project, despite putting put back a year.

Allseas’s Pioneering Spirit was originally due to have begun the mammoth project to remove the topside of the Brent Delta platform in the first half of 2016. The project is now scheduled for the 2017 lifting season.

Duncan Manning, business opportunity manager on the Brent project, said putting the removal of the 24,000 tonne topside into 2017 was “not a big issue” for the Shell.

Brent Delta is the first of the field’s four production platforms to be removed from the North Sea.

The twin-hulled Pioneering Spirit is 382 m long and 124 m wide. The vessel is so large it is able to straddle a platform and remove entire topsides in a single lift using horizontal lifting beams.

“This is 600,000 displacement vessel is mega project in its own right, with a project of this size and scale it’s taken some extra time to commission, in particular the lifting arms. There are 16 required for Brent Delta and the time line to be able to commission each of those 16 lifting arms is proving more challenging for this lifting season.

“It’s not a big issue for us. We will continue to prepare the platform and de-man it and wait for that commissioning to take place.

“In the meantime we continue to do all of the testing, assurance and then the test lift, this summer season and then lift the Yme [jack up] platform again to provide us some additional reassurance that actually the technology does work.”

Manning declined to reveal the cost of the topside removal and getting it back to shore, citing commercial confidentiality.

“This is multi-year multi-billion pound project. This is one component, of which clearly there are many.”

Shell continues to carry out preparatory work on Brent Delta ahead of the topside lift, including leg cutting, cellar deck strengthening and installing shear restraints. It is also ensuring the Able yard in Billingham is fully prepared to accept the 24,000 tonne topside module next year.

Manning said work was on schedule for the decommissioning and removal of the Brent Alpha and Bravo platforms, which ceased production in 2014.

He was speaking the Decom Offshore 2016 conference held in Aberdeen, which sold out in advance and brought together leading figures from the operator and supply chain as the industry appears to be giving ever more focus to the decommissioning sector.

Manning said: “It needed great engineering and innovation to install the facilities, now we need it again for decommissioning.

“We will continue to look for opportunities to improve and reduce costs.”

SOURCE

RELATED ARTICLES

This website and sisters royaldutchshellgroup.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, and shellnews.net, are owned by John Donovan. There is also a Wikipedia segment.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Comment Rules

  • Please show respect to the opinions of others no matter how seemingly far-fetched.
  • Abusive, foul language, and/or divisive comments may be deleted without notice.
  • Each blog member is allowed limited comments, as displayed above the comment box.
  • Comments must be limited to the number of words displayed above the comment box.
  • Please limit one comment after any comment posted per post.