LNG production at Shell’s Prelude gas processing plant in Western Australia restarts following 11-month closure
ABC KimberleyBy Ben Collins: 23 Jan 2021
“As for making money from this project, that’s extremely unlikely because the cost overruns and completion delays are in the horrendous category,”…
Key points:
- The facility was shutdown for 11 months after electrical and safety problems
- Some analysts hold concerns about the facility’s economic and environmental performance
- Shell has never revealed the cost of constructing Prelude
Liquified natural gas (LNG) production has restarted this month on the world’s largest floating object, Shell’s half-kilometre long Prelude gas processing facility.
The restart is much-needed good news after an 11-month shutdown following a technical issue only described as an “electrical trip” by Shell, and three incidents that the offshore energy regulator NOPSEMA described as “dangerous occurrences”.