Royal Dutch Shell Plc  .com Rotating Header Image

Tales of the Unexpected and Royal Dutch Shell Prelude FLNG

Tales of the Unexpected – 2nd in a series of articles by Bill Campbell, retired HSE Group Auditor, Shell International, about safety issues relating to the Shell Prelude FLNG project

A Prelude to disaster?

Introduction by John Donovan

On 28 December I broke the news that a whistleblower had supplied me with photographic evidence to support their concerns over the safety of the construction of Shell’s Prelude FLNG flagship vessel.  The Prelude insider source alleges that packages are being installed on the vessel by totally unqualified personnel and accuses management of a failure to understand standards and regulations and claims the construction work would never pass UK standards. The source has been intimately involved in the project and is genuinely concerned that warnings issued to Shell management (and other parties) have been ignored and financial considerations are taking priority over safety issues. His warnings prompted a regular contributor, Bill Campbell, the retired HSE Group Auditor of Shell International to author articles on the subject that take into account his decades long experience and expertise. This is the second in an intended series.

Tales of the Unexpected

By Bill Campbell

When the plans to install the LPG marine terminal on the banks of the River Forth were in development much resistance to these were forthcoming from the inhabitants of the local towns and villages. Opposition came mainly from the residents of Aberdour, the nearest community to the proposed terminal.  What were the implications they argued if vessels loaded with thousands of tonnes of hydrocarbon liquids got into difficulties, if the cargo spilled during collision or grounding, if the resultant vapour cloud ignited etc, it was too dangerous, not in our back yard please.

Despite these objections, and rightly so in my opinion, the development went ahead. Every agency you can think of had their input, this would be a world class operation, every precaution that could be taken would be, Esso and Shell would see to that, and so it transpired, the facilities well installed, maintained and operated have by any measure had an excellent safety record.  But despite the best laid plans of mice and men the unexpected materialised and the catastrophic consequences were averted just!

On a fine day, the story of the Ship that went AWOL

By all accounts the weather on 23 January 1993 was fine. The good ship Havkong was loading Butane at its jetty at the Braefoot Bay Terminal by Aberdour on the banks of the Firth of Forth.  Things were going just dandy.  At 18.50 hours however, when the ship had loaded 6000 tonnes of a nominated 15,000 tonnes the area was subjected to an unusually violent, and totally unexpected squall. This squall produced a veering westerly wind with gusts in the order of 80 knots superimposed on a mean wind speed of 60 knots.  The mooring lines failed and the ship began to move ahead along its berth driven by the wind. As she gained momentum the loading arms reached their limits and successfully disconnected with no spillage of Butane.

The Havkong began to swing under the influence of both the wind and the last of the moorings and drifted eastwards broadside to the wind. She narrowly cleared a ship on the other berth, which was loading ethylene, by approximately 20 metres. About eight minutes after breaking free her engine was ready for use and was used to keep the ship in the narrow deep-water channel between the berths and the offshore island as she drifted downwind while anchors were prepared. With a pilot aboard and with tug assistance she was eventually brought to anchor circa one mile east of the berth. If the vessel had run aground in Aberdour Bay, the emergency contingency plans would have entailed a precautionary evacuation of Aberdour, it would have been a national incident much reported and commented on, but luckily the vessel was finally anchored in Kirkcaldy Bay at approaching midnight when the emergency was declared over.

So the moral of the tale, if one exists, is that despite the best endeavours of all involved, if things can go wrong they will, and when you least expect them. Perhaps we can put the squall down to an Act of God, it had not been forecast, but the mooring procedures and equipment should have held the Ship on her moorings despite this but human error had to be a factor in that there were shortcomings in that respect, on that day.

In general it’s a good news story. The potential consequences of the incident were not realised.

Returning to the general theme with respect to Prelude Floating LNG. My concern is that this historically is the story of the Maritime transport of LPG and LNG. Incidents happen from time to time but consequences to date are limited. From 1964 to 2005 accident data list 22 spillages of LNG cargo during loading some of these spills causing fracture cracking of deck plates when the cryogenic liquid contacts with the carbon steel. The same data lists 19 LNG carrier vessel collisions and groundings, some pretty dramatic, but the saviour in all these events was the double skinned hull. So in terms of the gazillion or so ship miles and the ever increasing number of LNG carrier vessels the industry can with some merit say it has not lost a cargo or killed anyone and therefore it has an excellent safety record. Whether this is self-congratulatory without due cause is for others to judge. The risk analyst cannot disagree, if you accept, as the Industry appears to accept that the probability of spills and collisions are inevitable, but that you have put measures in place at considerable expense, such as double skinned hulls, then you deserve the benefit of this, do you not?

With respect to Prelude LNG operations we must assume grounding to be a negligible risk during normal operations since the vessel is located in an area with sea depths of 250 metres. Ship collision risks are ever present but history shows us that the combination of state of the art fenders and the strength of the hull would reduce the consequences of a collision between a carrier vessel and Prelude. The area where a collision could be less forgiving is the single point mooring at the bow of the vessel where the risers and anchor points are located.  These risks are mitigated by the standard approach of the carrier vessel towards the stern of Prelude and as I understand it Prelude will have at least a couple of tugs ever present to assist in the mooring operations. It may be improbable, but studies suggest that it would take a large vessel colliding broadside with its bow normal to a Prelude to potentially cause damage to the internal Cargo tanks of such a vessel.  It’s not known to the author how closely located Prelude will be to the main shipping channels offshore Northern Australia.  However Prelude will have radar to spot possible collision potential, in heavy fog for example, and its tugs would respond I assume to avert the danger.

As observed in the Braefoot Bay incident the magnetic couplings where the cargo lines attach to the carrier vessel did their job and these couplings have no doubt evolved to be even more reliable. Human error however as always remains as a factor.  LNG spills have occurred where significant damage to the deck plates resulted. The instantaneous and violent contraction of the metal on contact with the cryogenic liquid simply tears it apart. Overloading of tanks normally causes these spills, perhaps the Master fears being shortchanged so he loads his tanks to their capacity and in some cases the level control systems have been faulty or unserviceable. The ship Jules Verne on its maiden trip was out of service for 4 months after a cargo tank overflowed – so the damage can be significant.

Shell also had a similar problem when a discharging arm disconnected prematurely causing a star shaped fracture on the deck plate of its vessel the Methane Princess.  At risk with ship to ship transfers, a risk not encountered when the carrier vessel is berthed against a jetty, is that cargo spillage could not only effect the vessel being loaded but the Prelude also. The difficulty sometimes in mitigating against one hazard on an offshore installation is that you create yet another.  In order to safeguard against fracture cracking LNG spillage should be contained in a stainless steel tank normally filled with seawater. The seawater is necessary because the cryogenic liquid rapidly evaporates on contact lessening potential for deck fractures but the rapid evaporation produces copious amounts of methane vapour. It’s a case of being damned if you do or damned if you don’t.

Bill Campbell

ARTICLE ENDS

First article by Bill Campbell: Shell Prelude FLNG: loss of containment of hydrocarbons almost inevitable

Screen Shot 2014-02-12 at 13.15.35

Related articles

Pipelines and welding risks for Shell: Kashagan and Prelude (Article by an oil industry expert)

What should frighten stiff Royal Dutch Shell shareholders (Article by John Donovan)

Piper Alpha anniversary: ‘mockery’ of safety by bullying, says whistleblower

Royal Dutch Shell Prelude Safety Debate

Shell Plans Boat to Tap Gas Fields

Will Shell’s Prelude FLNG project be another white elephant? (Article by an oil industry expert)

Shell Bets on a Colossal Floating Liquefied Natural Gas Factory Off Australia (New York Times Article)

Royal Dutch Shell Prelude to disaster? (Article by John Donovan)

This website and sisters royaldutchshellgroup.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, and shellnews.net, are owned by John Donovan. There is also a Wikipedia segment.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Comment Rules

  • Please show respect to the opinions of others no matter how seemingly far-fetched.
  • Abusive, foul language, and/or divisive comments may be deleted without notice.
  • Each blog member is allowed limited comments, as displayed above the comment box.
  • Comments must be limited to the number of words displayed above the comment box.
  • Please limit one comment after any comment posted per post.