Shell Corrib Gas 12 years behind schedule and four times over budget

Extract from an article by Nick Webb published Sunday 02 March 2014 by Independent.ie

Screen Shot 2013-09-24 at 18.48.35THE controversial Corrib gas field is expected to come onstream by “mid 2015.” Gas was originally expected to flow from the Mayo field back in 2003. The project is now likely to be 12 years behind the original schedule. The cost of developing the field could be four times the initial estimate of €800m at over €3bn.

FULL ARTICLE

ADDED BY JOHN DONOVAN: “The Bad News” slide appeared in a 62 page Royal Dutch Shell internal PowerPoint presentation prepared in June 2000: “Excom Early Look Business Plan 2000″. Turned out to be chillingly accurate in relation to many Shell projects, including Sakhalin2 and the Alaska debacle.

*This website and sisters royaldutchshellgroup.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, shellnews.net, and shellwikipedia.com, are owned by John Donovan - more information here. There is also a Wikipedia segment, the Shell DPA Files, "Shell and the Spies", the Shell Leaks files, as well as books written and published by John Donovan - Kindle eBooks. Timeline of the Donovan Shell Feud. Toxic History of Royal Dutch Shell Group. Shell and the Donovans: The Full Media Record — 550+ Articles, 110 Books, 40 Years. *All created and supported by internet wizz, Nick Gill.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.